North West Public Works Transport and Roads terminates R137,5 million tender

North West Public Works Transport and Roads terminates R137,5 million tender with Ilima Projects-Tsoga Developers Joint Venture contracted to build government office complex in Vryburg

16 December 2009

North West Department of Public Works, Roads and Transport has terminated the R137,5 million contract with the construction company Ilima Projects-Tsoga Developers Joint Venture (JV), which was awarded a tender to build a government office complex, Mini-Garona, in Vryburg.

The decision was informed by the company’s “poor performance” on the project and their “failure to meet targets” as agreed to, in their 24 months contract with the department. The start date of the Vryburg government office building was 25 July 2006 and the expected completion date was 25 July 2008.

The construction company requested an extension, which was granted to at least finish the project by 12 October 2009, the dead line which they also failed to meet two months later. The stalled project has been compounded by numerous stops and starts in the past two years with the department coming within a whisker to terminate the contract last year.

The decision to show the Ilima Projects-Tsoga Developers Joint Venture the door followed a stern warning by MEC Mahlakeng Mahlakeng to other contractors that: “There will be no room for non-performance or cutting corners with shoddy workmanship. Contactors, including emerging ones, must begin to perform or risk being shown the door.

“We will be ruthless on underperforming contractors who waste valuable time and public funds on projects and in so doing compromise government’s ability to deliver services to the people,” Mahlakeng warned.

He said the termination of the Ilima Projects-Tsoga Developers Joint Venture, “had nothing at all” to do with the budget pressures his department was experiencing at the moment in the roads directorate or the companies’ court application for provisional liquidation.

It is expected that the department will set-up a professional team to assess the balance of work at the stalled Vryburg project and reconcile a bill of quantities. The move would give the department options to consider as a way forward in the next few months. These may include, going on an open tender for the completion of the remainder of the work still to be done in the New Year.

Meanwhile, Mahlakeng confirmed that Ilima Projects-Tsoga Developers Joint Venture, performance will be closely monitored at the 200 bed hospital in Brits.
The same Ilima Projects-Tsoga Developers Joint Venture was awarded a R465 million contract by the department in July 2008 to build the health facility for the provincial Department of Health and Social Development in the Bojanala district.

Contact:

Matshube Mfoloe
Cell: 082 305 4594

Issued by: Department of Public Works, Roads and Transport, North West Provincial Government
16 December 2009

No comments:

Post a Comment

Please Leave a message

Fishing Report South Africa